Design & installation Guide For McQuay MDS Multi System
Make sure the distance between two Suspenders is 620.4mmX790.0mm;
Use nut, Plat gasket and spring gasket to hang the unit though the suspender;
Adjust the distance between the bottom surface of unit and ceiling to be 35.0mm;
Make sure the installation of indoor unit is horizontal, and then tighten the nut;
Drainage pipe test
Drainage pipe must be smooth, and it should have a downward slope to make the condensated
water discharge fluently
The drainage pipe should not be installed up and down.
When connecting the drainage pipe, do not give outside force to the unit in order to protect the
unit.
A hose with 20mm diameter should be used to connect the inside and the outside of the
drainage pipe.
Insulated material (polyethylene with 8mm thickness) should be used to prevent the drainage
pipe from sweating.